Bekok-C Process-Power MOPU

Location: Indonesia


Fast track project (engineering to first gas) within 6 months utilizing second hand equipments/rig to replace Bekok-C CPP with a MOPU (Combined capacity of 165MMscfd and 4000bpd liquids) which comprises of;

  • •  Gas-Liquid Separation and slugcatcher
  • •  TEG Dehydration
  • •  Two stage compression
  • •  Full on-board power generation
  • •  Complete independent utilities
  • •  Integration to Bekok-C platform
  • •  Power supply to existing Bekok-C Complex and platforms


Synergy's Scope of Work

  • •  Topside Engineering
  • •  Hull Engineering
  • •  Field support
  • •  Operation support (manuals/procedures)


Key Project Achievements

  1.  Complete Piping/E&I deliverables generated from master PDMS model
  2. Meet project engineering schedule.
  3. Fit for purpose design meeting safety, international standards, and Petronas Technical Standards (PTS)