KE-38 Facilities & Power MOPU

Client: Pertamina Hulu Energi West Madura Offshore (PHE WMO)

Location: Indonesia


High priority project to ensure MOPU deployment to existing KE-38 wellhead platform to maintain production continuation for WMO.

Total capacity of 60MMscfd gas throughput, 20 MMscfd gas lift and 4000bpd liquids, comprising of;

  • •  Gas-Liquid Separation
  • •  2x50% Two stage compression
  • •  Gas lift compression
  • •  2x100% power generation for KE-38 field and utilities


Synergy's Scope of Work

  • •  Topside Engineering
  • •  Hull Engineering
  • •  Partial Hull Engineering
  • •  Start-up and Operating procedures


Key Project Achievements

  1.  Complete Detailed Engineering
  2. High priority and value engineering parallel to project execution to meet safety, international standards, and PHE standards